2026
Get a survey done. Tony is working on this.
Tasks for Jan to do: 1. Provide drawings for the design of the house.
Tasks for Jake to do: 1. Check our work periodically. 2. Meet with us and check in on project going forward.
Investigate our water line. We need to dig that up at the meter and see what kind of a water line we have.
Investigate our gas line, and come up with a plan for cedar house if we have no gas.
Do a shitty survey so we can come up with a house plan. -T
Find a foundation company. -T
Finalize drawings to submit for the permits.
Get all the permits in order
Dig a big ass hole.
Get the exit plumbing fixed
put in the foundation
Tap off water line?
Do we need a temporary power pole?
2027
bottom plates
floor joists
subfloor
1st story framing
Temporary electrical connection?