December 2026

Tony: 1. Get an existing conditions survey done. Tony is working on this. 2. Tony - start gantt chart, link to it from TonyDiethelm website, start building a project schedule 3. Ask engineer: can we get rid of old cedar roof and build a “deck roof”?

Jake:

Aline: 1. send Jan photos of all side of house (make sure includes roof lines & rise to run of all roof slopes) 2. measure and confirm the exact dimensions of old cedar house (including all rooms) 3. Nov and Dec: design a bathroom

  • ideal bathroom
  • make bathroom I could live with

4. pick a tub and measure 5. make 2 designs, something with stairs in both locations 6. figure out how small my office can be, do I have closet/storage in the office? yes I do. 7. Ask engineer: can we get rid of old cedar roof and build a “deck roof”?

Jan: 1. Provide drawings for the design of the house. 2. Keep helping with floor plan designs

“call” 811

Which permit are we trying to get? Addition? New construction? Duplex? Tony needs to have another meeting with city: what are the implications of doing an addition compared to new construction? Tell city what we are doing. Learn which permit we need to apply for? (Jake thinks our plans might end up being treated at duplex).


January 2027

Tony:

Jake: 1. Check our work periodically. 2. Meet with us and check in on project going forward.

Aline:

Jan:


February 2027

Shop around for an engineer. They will need to look over Jan's plans.

Investigate our gas line, and come up with a plan for cedar house if we have no gas.

Find a foundation company that is run by women or people of color. -Tony and Jake

Finalize drawings to submit for the permits.

Get all the permits in order

Dig a big ass hole.


March 2027 and Beyond

Get the exit plumbing fixed

put in the foundation

Tap off water line?

Do we need a temporary power pole?

bottom plates

floor joists

subfloor

1st story framing

Temporary electrical connection?