2026
Get the foundation ready for next year
Get all the permits in order
Dig a big ass hole.
Get the exit plumbing fixed
put in the foundation
2027
get it waterproof
bottom plates
floor joists
subfloor
1st floor framing
Temporary electrical connection? When should we do this?
1st floor sheathing
floor joists again
subfloor again
second floor framing
second floor sheathing
roof joists
roof sheathing
ice/water shield + flashing
roofing
window/door flashing
window/door install
Get it functional
electrical install
plumbing install
"Finish" it
insulation
drywall
Paint
flooring install. Should do last so we don't fuck it up? PITA to do UNDER trim, do before the trim.
trim
__Bath and Kitchen__
tubs, toilets, cabinets, appliances
counters/
counter tops
sinks