2026

Get the foundation ready for next year

Get all the permits in order

Dig a big ass hole.

Get the exit plumbing fixed

put in the foundation

2027

get it waterproof

bottom plates

floor joists

subfloor

1st floor framing

Temporary electrical connection? When should we do this?

1st floor sheathing

floor joists again

subfloor again

second floor framing

second floor sheathing

roof joists

roof sheathing

ice/water shield + flashing

roofing

window/door flashing

window/door install

Get it functional

electrical install

plumbing install

"Finish" it

insulation

drywall

Paint

flooring install. Should do last so we don't fuck it up? PITA to do UNDER trim, do before the trim.

trim

__Bath and Kitchen__

tubs, toilets, cabinets, appliances

counters/

counter tops

sinks